Â鶹´«Ã½

Skip to main content
Start of main content

Wareham Dam interim spillway repairs

April 27, 2023

Current View
of

Â鶹´«Ã½¡¯s Irfan Maan discusses spillway repairs at Wareham Dam in Yukon with Canadian Dam Association Bulletin

The interim spillway repairs at Wareham Dam are complete. Â鶹´«Ã½¡¯s Senior Civil Engineer, Irfan Maan, explains the scope of work that was carried out at the dam outside of Mayo, Yukon including a site investigation, interim design drawings, and construction. Impressively, the team completed the project under a tight schedule at a remote site and in the middle of winter all while the Covid-19 pandemic was causing supply chain issues. Thanks to the combined works, the spillway is now protected from imminent failure and further degradation. The interim measures will be applied until a permanent solution is engineered and constructed.?

End of main content
To top